# Living Through a Kitchen Remodel: Six Weeks Without a Kitchen in Grimes

- [Blake Daniels](https://busybuildersiowa.com/author/blake-daniels/)
- October 28, 2026
- [Kitchen Remodeling](https://busybuildersiowa.com/category/kitchen-remodeling-blog/), [Remodeling](https://busybuildersiowa.com/category/remodeling/)

![Temporary kitchen on a folding table in a dining room with plastic sheeting over the doorway to a gutted kitchen](https://busybuildersiowa.com/wp-content/uploads/2026/09/living-through-a-kitchen-remodel-grimes.png)

The hardest part of a kitchen remodel is not the money. It is dinner on a Tuesday in week four. This guide is about the living-through-it side of a Grimes kitchen remodel: how long the kitchen is really out of service, how to set up a temporary kitchen that works, what the crew tells you and when, and the decisions to make before demo so the six weeks do not become ten.

**TLDR:** A full **kitchen remodel** with Busy Builders runs about 6 to 12 weeks from estimate through final punch, and the kitchen itself is unusable for roughly four to six of those weeks. Set up a temporary kitchen with a sink you can reach, a microwave, a countertop oven and a fridge before demo day. Expect a text before each trade day. Make every selection before demo, because the change you make in week three is the week you add.

---

## How long you are really without a kitchen

The estimate-to-done window is longer than the no-kitchen window, and the difference is worth understanding. A full kitchen remodel runs about 6 to 12 weeks from estimate and approval through installation and final punch; delivery lead times, permitting and trade scheduling drive the spread. The kitchen is torn out for only part of that.

**Pro Tip 1:** Count the no-kitchen weeks from demo to the day the sink is reconnected, not to the end of the job. Trim, touch-up and the last light fixture happen with a working kitchen.

Phase Kitchen usable? Typical duration

Estimate, selections, ordering, permit Yes 2 to 5 weeks

Demo No 1 to 2 days

Rough plumbing, electrical, inspection No 3 to 5 days

Drywall, paint No 4 to 6 days

Cabinets set No 2 to 4 days

Countertop template and wait No sink 7 to 14 days

Countertop install, sink and plumbing hookup Yes, from this day 1 to 2 days

Backsplash, appliances, trim, punch Mostly 1 to 2 weeks

Four to six weeks with no sink is the honest number for a Grimes kitchen with no structural changes. The countertop wait in the middle is the stretch everyone forgets.

**Pro Tip 2:** Ask whether the crew can set a temporary laminate top and reconnect the sink during the countertop wait. On some layouts it is a few hundred dollars and buys back two weeks of dishes.

## The temporary kitchen that actually works

**Pro Tip 3:** Build the temporary kitchen the weekend before demo, not the night of. Test it by cooking one dinner in it.

The table below is the setup that works for most Grimes families.

Item Where Why

Sink Laundry room or bathroom sink with a dish tub You need running water for dishes, not just drinking

Refrigerator Garage or dining room; the crew moves it Keep the old fridge running until the new one is in

Microwave and countertop oven Folding table in the dining room on its own circuit Two heating appliances on one circuit trips the breaker

Electric kettle and coffee maker Same table, different outlet Morning survival

Slow cooker or electric skillet Same table Real dinners without a range

Paper plates for the first week Anywhere Dishwashing in a bathroom sink gets old fast

Pantry bins Dining room shelves or a closet Everything from the kitchen cabinets, sorted by use

Grill Patio Summer and fall dinners

Two circuits are the detail people miss. A microwave and a toaster oven together draw more than a 15-amp circuit gives you.

**Pro Tip 4:** Plan your meals for the no-kitchen weeks like a camping trip: one-pot, sheet-pan, grill, slow cooker, and two nights a week out. It costs money; budget it.

## What the crew tells you, and when

Communication is what customers mention most in our reviews: being kept informed, and being able to text the crew with additions mid-project. Here is what that looks like on a kitchen.

**Pro Tip 5:** Expect a text the night before each trade day naming who is coming and what they will do. If you are not getting one, ask for it.

Moment What you should hear from us

Before demo Start date, what to clear out, where the fridge goes, dust protection plan

Day the walls open What we found: wiring condition, any moisture, anything that changes scope

Before rough-in inspection Walkthrough of outlet and fixture locations; last chance to move them

Countertop template Confirmed slab, seam locations, sink model on site

Each trade day Night-before text

Quiet days Why nothing is happening today (mud drying, template lead time, inspection)

Punch list A written list you review together

A customer with a small project noted in a review that we scheduled it quickly and cleaned up before leaving. On a six-week kitchen, cleanup is daily, not just at the end.

**Pro Tip 6:** Dust is the complaint we hear most from families who did not plan for it. Ask for plastic zip walls at every doorway and a box fan exhausting out a window during demo and sanding.

## Decisions to make before demo

**Pro Tip 7:** Every decision made after demo adds days. Tile, counters, fixtures, appliances, paint, hardware, lighting: all chosen and ordered before the first cabinet comes off the wall.

Decision Deadline Why

Cabinets ordered and confirmed 4 to 8 weeks before demo Longest lead item

Appliances chosen, specs to the electrician Before rough electrical Circuits and outlet locations depend on them

Tile and counters chosen Before the estimate Both are budget lines that move; both have lead times

Sink and faucet on site Before countertop template The fabricator cuts to the sink you own

Paint colors Before drywall finish First coat goes on before cabinets

Hardware and lighting Before trim day Small items that stall the last week

Illustrative scenario: A Grimes family sets up the temporary kitchen in the dining room with two circuits, moves the fridge to the garage, and meal-plans the no-kitchen weeks. Demo Monday, sink reconnected day 29. Six weeks and two days from demo to punch, about $54,000.

Illustrative scenario: A couple in [Grimes](https://busybuildersiowa.com/grimes/) picks the countertop after cabinets are set, then changes the sink model. The template is redone and the slab waits for the new sink. Four no-kitchen weeks become seven.

Illustrative scenario: A family in a 1970s ranch opens the walls and finds old wiring the electrician will not tie into. Two extra days and about $2,200 from the reserve. The night-of-demo call is why it was a decision and not a surprise.

## The small things that make the weeks livable

**Pro Tip 8:** If your home was built before 1978, ask about lead-safe practices for demo. The [EPA’s Renovation, Repair and Painting program](https://www.epa.gov/lead/lead-renovation-repair-and-painting-program) sets the rules for disturbing old paint.

**Pro Tip 9:** Keep the pets and the toddler out of the work zone with a real barrier, not a request. Nails, tools and open walls do not care who is curious.

**Pro Tip 10:** Choose [ENERGY STAR](https://www.energystar.gov/) appliances at selection time and have them delivered to the garage a week before install day. A backordered dishwasher is the most common reason the last week slips.

**Pro Tip 11:** If you are financing, have it closed before demo. The [Consumer Financial Protection Bureau’s owning-a-home guide](https://www.consumerfinance.gov/owning-a-home/) walks through the options; a HELOC that funds in week two stalls the cabinet order.

**Pro Tip 12:** Book nothing for the end date. Book the dinner party for two weeks after, and if the kitchen is done early, you have a quiet two weeks in a new kitchen.

## Frequently Asked Questions

**Q1: How long will I be without a kitchen during a remodel?** About four to six weeks on a full remodel with no structural changes: from demo to the day the sink is reconnected after countertops. The whole project, from estimate to final punch, runs about 6 to 12 weeks on our jobs.

**Q2: Can I live in the house during a kitchen remodel?** Yes, most families do. Set up a temporary kitchen with a reachable sink, a microwave and a countertop oven on separate circuits, and the fridge nearby. Plan meals for those weeks, and ask the crew for dust walls at every doorway.

**Q3: What will the crew tell me during the job?** A night-before text for each trade day, a call the day the walls open with what was found, a walkthrough before the rough-in inspection, and a written punch list at the end. Communication is what customers mention most in our reviews, so ask for that rhythm from day one.

**Q4: What causes the no-kitchen weeks to grow?** Late decisions: a countertop chosen after cabinets are set, a sink swap after template, an appliance that arrives late. Older homes add a day or two for what the walls hide. Decide everything before demo and keep a 10 to 15 percent reserve.

**Q5: How do I start?** Call: [844-435-9800](tel:844-435-9800) for a walkthrough. We will map the no-kitchen weeks on a calendar with you before you sign anything.

## Key Takeaways

- **The real number:** Four to six weeks without a sink; 6 to 12 weeks estimate to done.
- **The setup:** Reachable sink, two circuits, fridge nearby, meal plan, dust walls.
- **The rhythm:** Night-before texts, a call when the walls open, a walkthrough before inspection.
- **The rule:** Decide everything before demo. Changes after demo are weeks, not days.

## Map Your Six Weeks Before You Sign

Busy Builders is a registered Iowa contractor with 1,285+ completed projects across Central Iowa since 2020. Every [kitchen remodeling](https://busybuildersiowa.com/kitchen-remodeling/) estimate comes with a trade-day calendar so you know which weeks the kitchen is out. [Contact us](https://busybuildersiowa.com/contact-us/) for a free consultation. Written warranty on workmanship (details provided in your contract).

Call: [844-435-9800](tel:844-435-9800)

---

*Disclaimer: This article is for general information and is not project-specific, financial or legal advice. Cost figures are planning estimates that vary by scope, materials, site conditions and current pricing. Timelines are typical ranges and are not guaranteed. Permit requirements vary by city and jurisdiction; verify current requirements with the City of Grimes before starting any project. Consult a registered contractor; electrical and plumbing work is performed by licensed subcontractors. Financing decisions should be reviewed with a qualified financial professional.*

Busy Builders | Full-Service Construction and Remodeling | Serving Central Iowa Since 2020

[PrevPrevious GuideAttached Garage Additions in Central Iowa: Tying Into the House, Frost Footings and Fire Separation](https://busybuildersiowa.com/attached-garage-additions-central-iowa/)

#### In This Guide

Want A Free Quote?

- Keep Reading

## More Construction and Remodeling Guides

### [Attached Garage Additions in Central Iowa: Tying Into the House, Frost Footings and Fire Separation](https://busybuildersiowa.com/attached-garage-additions-central-iowa/)

Oct 26, 2026

An attached garage is an addition. Frost footings, the roof tie-in, the fire-rated wall and door, and what makes it cost more than a

[Read More](https://busybuildersiowa.com/attached-garage-additions-central-iowa/)

### [Kitchen Layouts That Work in 1990s Two-Story Homes in Ankeny and Johnston](https://busybuildersiowa.com/kitchen-layouts-1990s-two-story-ankeny-johnston/)

Oct 23, 2026

The closed 1990s kitchen with the peninsula and the wall to the family room. Three layouts that fix it, what the beam costs, and

[Read More](https://busybuildersiowa.com/kitchen-layouts-1990s-two-story-ankeny-johnston/)

### [Primary Bath vs Hall Bath in Clive: Where the Money Goes](https://busybuildersiowa.com/primary-bath-vs-hall-bath-clive/)

Oct 21, 2026

Same trades, same tile brand, $40,000 apart. Where the money goes in a Clive hall bath versus a primary bath, using ranges we have

[Read More](https://busybuildersiowa.com/primary-bath-vs-hall-bath-clive/)

```json
[{"@context":"https:\/\/schema.org","@graph":[{"@type":"Place","@id":"https:\/\/busybuildersiowa.com\/#place","geo":{"@type":"GeoCoordinates","latitude":"41.6060855","longitude":"-93.8051957"},"hasMap":"https:\/\/www.google.com\/maps\/search\/?api=1&amp;query=41.6060855,-93.8051957","address":{"@type":"PostalAddress","streetAddress":"111 S 49th Street","addressRegion":"IA","postalCode":"50265","addressCountry":"US","addressLocality":"West Des Moines"}},{"@type":["GeneralContractor","Organization"],"@id":"https:\/\/busybuildersiowa.com\/#organization","name":"Busy Builders","url":"https:\/\/busybuildersiowa.com","sameAs":["https:\/\/www.facebook.com\/BusyBuilderz","https:\/\/www.bbb.org\/us\/ia\/west-des-moines\/profile\/remodel-contractors\/busy-builders-llc-0664-32137323","https:\/\/www.desmoinesregister.com\/press-release\/story\/30329\/busy-builders-expands-services-to-custom-home-building-in-central-iowa\/","https:\/\/nextdoor.com\/pages\/busy-builders-west-des-moines-ia\/","https:\/\/busybuildersllc.quora.com\/Busy-Builders-LLC-is-a-West-Des-Moines-IA-General-Contractor-company-focused-on-home-enhancement-through-remodeling-and","https:\/\/www.city-data.com\/business-entities\/IA\/BUSY-BUILDERS-LLC-644057-IA.html","https:\/\/www.homeadvisor.com\/rated.BusyBuildersLLCHome.125418287.html","https:\/\/share.google\/CwLFRDUlwAA3jdC6I","https:\/\/maps.app.goo.gl\/DigdFS58XfGad2h57","https:\/\/www.trustindex.io\/reviews\/busybuildersiowa.com","https:\/\/www.wikidata.org\/wiki\/Q139699968"],"email":"info@busybuildersiowa.com","address":{"@type":"PostalAddress","streetAddress":"111 S 49th Street","addressRegion":"IA","postalCode":"50265","addressCountry":"US","addressLocality":"West Des Moines"},"logo":{"@type":"ImageObject","@id":"https:\/\/busybuildersiowa.com\/#logo","url":"https:\/\/busybuildersiowa.com\/wp-content\/uploads\/2024\/11\/cropped-cropped-Untitled-design-57.png","contentUrl":"https:\/\/busybuildersiowa.com\/wp-content\/uploads\/2024\/11\/cropped-cropped-Untitled-design-57.png","caption":"Busy Builders","inLanguage":"en-US","width":"512","height":"147"},"priceRange":"$$$","openingHours":["Mo,Tu,We,Th,Fr,Sa,Su 08:00-18:00"],"description":"Busy Builders is a full-service home construction and remodeling contractor based in West Des Moines and serving homeowners across Central Iowa, including Des Moines, Ankeny, Waukee, Urbandale, and surrounding communities. Founded in 2020 after decades in the trades, the company specializes in custom home building, whole-home remodeling, kitchen and bathroom renovations, basement finishing and remodeling, home additions, and custom deck construction. Every project is managed from design through completion with a focus on transparent communication, honest pricing, detailed planning, and craftsmanship built to handle everyday life, helping families create functional, beautiful spaces that are made to last for generations. We are a registered and insured Iowa contractor; Iowa Contractor Registration #C140184.","legalName":"Busy Builders LLC","foundingDate":"2020-01-01","numberOfEmployees":{"@type":"QuantitativeValue","value":"90"},"location":{"@id":"https:\/\/busybuildersiowa.com\/#place"},"image":{"@id":"https:\/\/busybuildersiowa.com\/#logo"},"telephone":"844-435-9800"},{"@type":"WebSite","@id":"https:\/\/busybuildersiowa.com\/#website","url":"https:\/\/busybuildersiowa.com","name":"Busy Builders","alternateName":"Busybuildersiowa.com","publisher":{"@id":"https:\/\/busybuildersiowa.com\/#organization"},"inLanguage":"en-US"},{"@type":"ImageObject","@id":"https:\/\/busybuildersiowa.com\/wp-content\/uploads\/2026\/09\/living-through-a-kitchen-remodel-grimes.png","url":"https:\/\/busybuildersiowa.com\/wp-content\/uploads\/2026\/09\/living-through-a-kitchen-remodel-grimes.png","width":"1250","height":"1250","caption":"Temporary kitchen on a folding table in a dining room with plastic sheeting over the doorway to a gutted kitchen","inLanguage":"en-US"},{"@type":"BreadcrumbList","@id":"https:\/\/busybuildersiowa.com\/living-through-a-kitchen-remodel-grimes\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":"1","item":{"@id":"https:\/\/busybuildersiowa.com","name":"Home"}},{"@type":"ListItem","position":"2","item":{"@id":"https:\/\/busybuildersiowa.com\/category\/kitchen-remodeling-blog\/","name":"Kitchen Remodeling"}},{"@type":"ListItem","position":"3","item":{"@id":"https:\/\/busybuildersiowa.com\/living-through-a-kitchen-remodel-grimes\/","name":"Living Through a Kitchen Remodel: Six Weeks Without a Kitchen in Grimes"}}]},{"@type":"WebPage","@id":"https:\/\/busybuildersiowa.com\/living-through-a-kitchen-remodel-grimes\/#webpage","url":"https:\/\/busybuildersiowa.com\/living-through-a-kitchen-remodel-grimes\/","name":"Living Through A Kitchen Remodel: Six Weeks Without A Kitchen In Grimes","datePublished":"2026-10-28T10:00:00-05:00","dateModified":"2026-10-28T10:00:00-05:00","isPartOf":{"@id":"https:\/\/busybuildersiowa.com\/#website"},"primaryImageOfPage":{"@id":"https:\/\/busybuildersiowa.com\/wp-content\/uploads\/2026\/09\/living-through-a-kitchen-remodel-grimes.png"},"inLanguage":"en-US","breadcrumb":{"@id":"https:\/\/busybuildersiowa.com\/living-through-a-kitchen-remodel-grimes\/#breadcrumb"}},{"@type":"Person","@id":"https:\/\/busybuildersiowa.com\/author\/blake-daniels\/","name":"Blake Daniels","description":"Blake Daniels founded Busy Builders in 2020. Read his guides on home building, remodeling, basements, decks and additions across Central Iowa.","url":"https:\/\/busybuildersiowa.com\/author\/blake-daniels\/","image":{"@type":"ImageObject","@id":"https:\/\/busybuildersiowa.com\/wp-content\/litespeed\/avatar\/1b3807b32c8c2fafb64a2eddb79753af.jpg?ver=1769728917","url":"https:\/\/busybuildersiowa.com\/wp-content\/litespeed\/avatar\/1b3807b32c8c2fafb64a2eddb79753af.jpg?ver=1769728917","caption":"Blake Daniels","inLanguage":"en-US"},"sameAs":["https:\/\/busybuildersiowa.com\/","https:\/\/www.facebook.com\/BusyBuilderz\/","https:\/\/twitter.com\/builders_busy","https:\/\/www.tiktok.com\/@busybuilders","https:\/\/www.youtube.com\/@BusyBuildersLLC"],"worksFor":{"@id":"https:\/\/busybuildersiowa.com\/#organization"}},{"@type":"BlogPosting","headline":"Living Through A Kitchen Remodel: Six Weeks Without A Kitchen In Grimes","keywords":"kitchen remodel","datePublished":"2026-10-28T10:00:00-05:00","dateModified":"2026-10-28T10:00:00-05:00","articleSection":"Kitchen Remodeling, Remodeling","author":{"@id":"https:\/\/busybuildersiowa.com\/author\/blake-daniels\/","name":"Blake Daniels"},"publisher":{"@id":"https:\/\/busybuildersiowa.com\/#organization"},"description":"How long a Grimes kitchen is really out of service, how to set up a temporary kitchen, what the crew tells you and when, and the decisions to make before demo.","name":"Living Through A Kitchen Remodel: Six Weeks Without A Kitchen In Grimes","@id":"https:\/\/busybuildersiowa.com\/living-through-a-kitchen-remodel-grimes\/#richSnippet","isPartOf":{"@id":"https:\/\/busybuildersiowa.com\/living-through-a-kitchen-remodel-grimes\/#webpage"},"image":{"@id":"https:\/\/busybuildersiowa.com\/wp-content\/uploads\/2026\/09\/living-through-a-kitchen-remodel-grimes.png"},"inLanguage":"en-US","mainEntityOfPage":{"@id":"https:\/\/busybuildersiowa.com\/living-through-a-kitchen-remodel-grimes\/#webpage"}}]},{"@context":"https:\/\/schema.org","@type":"FAQPage","mainEntity":[{"@type":"Question","name":"Q1: How long will I be without a kitchen during a remodel?","acceptedAnswer":{"@type":"Answer","text":"About four to six weeks on a full remodel with no structural changes: from demo to the day the sink is reconnected after countertops. The whole project, from estimate to final punch, runs about 6 to 12 weeks on our jobs."}},{"@type":"Question","name":"Q2: Can I live in the house during a kitchen remodel?","acceptedAnswer":{"@type":"Answer","text":"Yes, most families do. Set up a temporary kitchen with a reachable sink, a microwave and a countertop oven on separate circuits, and the fridge nearby. Plan meals for those weeks, and ask the crew for dust walls at every doorway."}},{"@type":"Question","name":"Q3: What will the crew tell me during the job?","acceptedAnswer":{"@type":"Answer","text":"A night-before text for each trade day, a call the day the walls open with what was found, a walkthrough before the rough-in inspection, and a written punch list at the end. Communication is what customers mention most in our reviews, so ask for that rhythm from day one."}},{"@type":"Question","name":"Q4: What causes the no-kitchen weeks to grow?","acceptedAnswer":{"@type":"Answer","text":"Late decisions: a countertop chosen after cabinets are set, a sink swap after template, an appliance that arrives late. Older homes add a day or two for what the walls hide. Decide everything before demo and keep a 10 to 15 percent reserve."}},{"@type":"Question","name":"Q5: How do I start?","acceptedAnswer":{"@type":"Answer","text":"Call: 844-435-9800 for a walkthrough. We will map the no-kitchen weeks on a calendar with you before you sign anything."}}]}]
```